Share |







CONSTRUCTION UPDATES
1 2Next

Progress as of 2/17/2012
Last Sunday morning for the first time we held children and youth classes in our new addition. It was exciting to see all the kids in this new space and also to see the excitement on their faces. One little girl was heard saying, “Mommy, I just love new classrooms!!” Then on Wednesday evening, there were kids, youth and adults using the new space. While there are still a few minor touch ups that need to be completed, the new addition looks great. On Monday, February 13, the renovation of portions of the existing building began with Lakeside volunteers stepping in to start tearing out areas in the southern and eastern corridors of the building. The turnout of volunteers has been great and they have done an excellent job. At this point, with the work they have completed to date, we think we are ahead of schedule and believe we will be done with our part of the work well before our goal of February 27. So if you are into destruction, there’s still time to get in on the fun. But don’t wait around too long or it will all be done!!! Saturday, February 18 is going to be a big day with lots of folks working, including a large number of our youth. So come on out and enjoy the fun!!! Hope to see you there!!! (Feb 17, 2012)

Progress as of 1/16/2012
HOB has now installed ceramic tile in the restrooms, painted all classrooms, hung ceiling grid and dropped in light fixtures in all the classrooms. This week they will begin flooring in the restrooms, installation of doors and casework. They will also paint the exposed ceiling. HOB indicates that they are on schedule for Lakeside to be able to start utilizing the new addition by mid-February. (Jan 16, 2012)

Progress as of 12/26/2011
Things continue to move along smoothly with our new construction. Last week, HOB completed the EIFS (exterior wall treatment for the north wall of the new addition)and installed all storefront and strip windows. The curtainwall (cross) windows installation will begin on this week. All gypsum board has been hung and drywall finishing is aprox. 50% complete. 5 of the classrooms have been primed. HOB began the demo of the existing wall between the existing building and the new addition and will install shoring this week. Currently we are a couple of weeks ahead of schedule. HOB anticipates that we will be in the new addition by mid to late February. They will begin work in the existing building to renovate the south and east corridors at that same time. (Dec 27, 2011)

Progress as of 12/19/2011
As of December 19, HOB has completed sanitary sewer connections, the exterior brick on the east and south sides of the new addition, and will complete the exterior treetment (EIFS) this week. The electrical, HVAC and plumbing rough-in is complete and B&B has begun pulling wire. Much drywall has been hung and finishing has begun and will continue this week. HOB will demo the wall between the existing addition and the new addition this week to allow installation of the shoring beam. (Dec 20, 2011)

Progress as of 12/5/11
HOB has made some exciting progress to date. The masons have finished constructing the entire east wall and are approximately 70% done on the south side. The roofing is approx 95% complete and they are installing flashing. The frame work (interior metal studs) on the inside of the new addition are almost completed and the plumbing and electric rough-in is mostly done. Insulation and drywall was delivered to the site last week so this drywall should begin to go up soon. (Dec 05, 2011)

Progress as of 11/14/2011
This past week, HOB continued installing exterior metal studs and exterior sheathing. They also poured the slab floor for the new addition. (Nov 14, 2011)

Progress as of 11/7/11
This past week, HOB roughed-in the underground plumbing and started spreading rock in preparation for pouring our concrete slab floor. The weather will determine what day they will actually pour concrete. HOB also started erecting exterior metal studs. This work will continue this week along with the exterior sheathing. (Nov 07, 2011)

Progress as of 10/31/2011
HOB finished pouring footings on Monday of last week and began laying concrete block foundation walls. This work was completed on Friday. Structural steel was delivered on Tuesday and the main steel has been erected. HOB began detailing & installing metal deck last week and should have this work completed by Wednesday of this week. HOB will begin installing plumbing that will go under the slab this week and possibly start putting up stud walls by the end of the week. (Oct 31, 2011)

Foundations Being Finished Today
This morning they are taking great care to finish the foundation for our new children's area! Actually, the real foundation is Jesus Christ our Lord... but we'll let these guys pour the concrete anyway. (Oct 24, 2011)

Progress as of 10/24/2011
This past week, HOB completed the installation of the sanitary sewer and switched the service over to the new line. In addition, they installed a new storm sewer connection for the new addition. With this work completed, HOB was able to dig building foundations and began pouring concrete footings last Friday. They should complete pouring footings (54 yards of concrete) today. All of this work is being done in preparation for the structural steel delivery set for Tuesday, 10/25/2011. Erection of the steel framing should begin midweek this week. (Oct 24, 2011)

1 2Next
 
We're excited about the activity you're currently seeing around our facility. God has been bringing families to Lakeside and we're trying to make sure we continue to be able to serve them as they grow in relationship with Jesus and each other. In fact, we are convinced that God has a plan for each person that walks through our doors so we are making room and investing in the future of everyone with our current expansion.

We are expanding and building a children's facility to better equip the next generation of Christ-followers because we know they are our future and that God cares for little people in a big way. We are also knocking down walls and renovating our existing building to accommodate our student ministry's rapid growth as well as clearing and remodeling our lobby to help enhance the building of relationships in a warm and welcome space.

We will be posting construction updates so check back often to keep up on the progress as well as check out some of the renderings of what the finished space will look like.

If you're new to Lakeside or just checking us out, we encourage you to come see for yourself. We're more than a building. We're a family that is committed to becoming more like Jesus and inviting as many people as we can to find out how he has changed us and can do the same for them. We're gonna make sure there is room for you.

 
Click here to see renderings of the
completed space.
 
Click here to see ongoing
construction pictures.
    All Material Copyright Lakeside Christian Church 2010  |  Privacy Statement   |  Terms Of Use  
Login   |  Register